Main INjector ExpeRiment v-A
September 12, 2008
| Overview | CD-3b Documentation| Other Documents|
Overview of Charge and Experiment
- MINERvA Overview (pdf)
- Review Agenda (pdf)
- Review Charge (pdf)
- Review Presentations by MINERvA Project Team
- Project Overview (pdf)
- Scintillators (WBS 1.0) WLS Fibers (WBS 2.0) and Clear Fiber Cables (WBS 4.0) (pdf)
- Phototubes (WBS 6.0) PMT Housing (WBS 5.0) and Electronics and DAQ (WBS 7.0) (pdf)
- Scintillator Plane Assembly (WBS 3.0) Frames Absorbers and Stand (WBS 8.0) and Module Assembly and Veto Wall (WBS 9.0) (pdf)
CD-3b Documentation
- Closeout Report from DOE CD-3b Review (pdf)
- Responses to recommendations from DOE CD-3b Review (pdf)
- DOE CD-3b Review Web page (web page with links)
- Results of and Responses to Site Preliminary Design Review
Other Documents
- Project Change Requests (web page with links)
- Project Monthly Reports (web page with links)
- Project Execution Plan (2/22/07 Version with signatures) (pdf)
- Acquisition Strategy (3.2MB pdf with signed signature page) or (323kB unsigned pdf)
- Project Management Plan (2/22/07 Version with signatures) (pdf)
- Technical Design Report (pdf)
- Resource Loaded Schedule (note: this schedule also includes tasks funded by NSF MRI grant)
- Microsoft Project File (40MB MS Project File)
- Gantt Chart (pdf)
- Critical Path (pdf)
- Costs (Note: unless otherwise indicated, the costs in this table are unburdened FY06$ base costs (pdf)
- Milestone GANTT Chart (pdf)
- Milestone Definitions (pdf)
- WBS Dictionary (1.9MB pdf)
- Risk Management (pdf)
- Safety Documentation